The exciting expansion of Edgar Sewter Primary School is due to start early December 2021. We will keep you up to date with the progress on this page!

Tuesday 27th September 2022 - we think the outside of our building looks just as smart as the inside.

Monday 26th September 2022 - the building is officially ours and our year 1 & 2 classes have moved in.

Friday 16th September 2022 - the new classrooms are nearly complete and we're very excited about moving in!

Tuesday 16th August 2022 - lots of progress around the school.

IMG_7640.jpg
IMG_7641.jpg
IMG_7642.jpg

Monday 1st August 2022 - new entrance and window to the year 5&6 area, as well as stud work for the new cloakroom.

IMG_7637.jpg
IMG_7638.jpg
IMG_7639.jpg

Friday 29th July 2022 - entrance to the new building from inside school. Plus the doorway that used to lead to the year 5&6 area has been blocked up.

Tuesday 5th July 2022 - the staff room has had a door way knocked through to access the year 5&6 area, and is also being made into two new rooms for interventions and meetings.

Monday 4th July 2022 - the roof tiles are ready to be finished off.

IMG_7557 (1).jpg
IMG_7558 (1).jpg
IMG_7559 (1).jpg

Tuesday 14th June 2022 - two classrooms and the library looking towards two rooms.

Wednesday 8th June 2022 - the roof is nearly there and the window frames have been delivered.

Wednesday 25th May 2022 - the roof is taking shape.

Tuesday 17th May 2022 - the site has been very busy and the building keeps on growing.

Tuesday 3rd May 2022 - the building is rising from the ground - we also have the new bicycle sheds in place (although not in use yet).

Friday 8th March 2022 - bricks and window frames are in place.

Monday 28th March 2022 - the concrete floor is in and the bricks have been delivered to start the walls.

Friday 18th March 2022 - we now have some steel work and the first bricks have been laid.

Friday 11th March 2022 - as you can see, the footings are in, maybe we'll see the building taking shape soon..

Monday 28th February 2022 - the playground looked different again when we returned after half term.

Tuesday 15th February 2022 - lots of activity this week, the playground is looking very different ..

Tuesday 8th February 2022 - this week we have our new playground and pathways in use. We have also changed the way we come into school as the old playground has been closed off ready to start the new building.

Wednesday 26th January 2022 - the tarmac is being laid for our new playground and pathways.

Wednesday 5th January 2022 - Digging out our new playground and pathways.

Thursday 9th December 2021 - Official 'breaking ground' Ceremony.

Monday 6th December 2021 - the contractor portacabins arrive on site.

Friday 3rd December 2021 - It's started! The bike shed is being moved....